Construction Updates

Last Updated: 31st March 2024

Stage Anticipated
Construction Start
Current
Construction /Phase
Anticipated
Title Release
Stage 70 October 2023 7 June 2024
Stage 71 & 72 October 2023 6 June/July 2024
The Sanctuary
(51 Tarwin Street)
November 2023 2 September 2024

 

 

 

PHASES OF CONSTRUCTION:
1. Plans & Permits Shire and Authority acceptance of documentation including engineering design to allow physical works to commence on site.
2. Earthworks Preparation of the site to achieve design lot levels including site scrape, shaping of the existing ground and construction of retaining walls where required.
3. Sewer & Drainage Installation of sewer and drainage to service the development of the stage.
4. Road boxing, Kerb & Channel Prepare the ground and start to construct the lower layers of the road pavement. Install water and gas mains and construct kerb and channel.
5. Electrical & Telecommunications Trench and install electrical and telecommunications services once kerb and channel works are complete.
6. Footpaths & Asphalt Prepare the ground in readiness to construct footpaths. Construct footpaths and topsoil nature strips. Construction of middle pavement layers and placement of asphalt.
7. Completion & Inspection of works Shire and Service Authority works inspections and sign off to constructed works including roads and services. Provision of final documentation to the Shire to facilitate a Statement of Compliance for the development Stage.
8. Titles Office & Settlement Registration of individual lots from each Stage occurs at the Titles Office and your block is now ready for you to settle and start the construction of your new home. Congratulations!