Construction Update

15th October 2018
Stage Anticipated
Construction Start
Current
Construction /Phase
Anticipated
Title Release
Stage 30 February 2018 Phase 8 September 2018
Stage 46 & 47 July 2018 Phase 3 January 2019
Stage 48 & 49 September 2018 Phase 2 March 2019
Stage 50 & 51 November 2018 Awaiting June 2019
Stage 52 & 53 March 2019 Awaiting October 2019
Stage 54 & 55 April 2019 Awaiting November 2019
Stage 56 & 57 August 2019 Awaiting February 2020
Construction Progress Phases
1. Plans & Permits Shire and Authority acceptance of documentation including engineering design to allow physical works to commence on site.
2. Earthworks Preparation of the site to achieve design lot levels including site scrape, shaping of the existing ground and construction of retaining walls where required.
3. Sewer & Drainage Installation of sewer and drainage to service the development of the stage.
4. Road boxing, Kerb & Channel Prepare the ground and start to construct the lower layers of the road pavement. Install water and gas mains and construct kerb and channel.
5. Electrical & Telecommunications Trench and install electrical and telecommunications services once kerb and channel works are complete.
6. Footpaths & Asphalt Prepare the ground in readiness to construct footpaths. Construct footpaths and topsoil nature strips. Construction of middle pavement layers and placement of asphalt.
7. Completion & Inspection of works Shire and Service Authority works inspections and sign off to constructed works including roads and services. Provision of final documentation to the Shire to facilitate a Statement of Compliance for the development Stage.
8. Titles Office & Settlement Registration of individual lots from each Stage occurs at the Titles Office and your block is now ready for you to settle and start the construction of your new home. Congratulations!